Week 7: Infrastructure You Don't See

Water, sewage and power as capacity-constrained networks — where headroom runs out, and how one quiet failure cascades into the next.

19 April 2027

Open the slides

The argument

Every utility in the studio is a network with a flat performance curve and a cliff at the end of it, so the only real infrastructure decision a designer makes is how much headroom to pay for while nothing yet looks wrong.

What you will learn

Theory into practice

The deck walks through where each of these lands, slide by slide, against the cascade the corridor actually runs.

Simulation mapping

Theory moveCities: Skylines II mechanicWhat students should watch happen
Star: infrastructure is invisible until breakdownthe water, sewage and electricity info-views, and their production-versus-consumption barsThe bars move for roughly three weeks of simulated time before a single citizen notification fires
Hughes: the reverse salient caps the whole systemthe single trunk main out of the Wensley Bank pumping stationAdding pipe inside Ombersley Flats raises nothing; the district’s capacity stays the pump’s number
Perrow: tight coupling turns a fault into a cascadethe water → sewage → water-pollution → health → budget chainOne over-capacity treatment plant ends up moving the healthcare budget slider
Tarr: waste is moved, not removedthe sewage outfall and the ground- and water-pollution overlaysThe issued failure branch illustrates an exposed intake; the personal Week 3 intake remains upstream
Graham and Marvin: networks splinter along their own topologypipe-graph distance from the pumping stationCompare affected districts without inferring outage order from pipe distance alone
— (mechanic with no single theory anchor)the per-service budget slidersDropping the water slider to 80% reduces delivered output, not only the monthly cost

Evidence standard. Named interface fields are direct readouts. Calculations shown from those fields are derived measures. Every fixed scenario value on this page is a worked hypothetical, not a captured run. See resources and evidence for access arrangements and worksheets.

The decision this week

Fiscal performance against livability, forced by how much headroom to install at the Wensley Bank pumping station and the Farrant Row treatment plant before the demand exists. The deck works both the underbuilt and overbuilt cases in full. Mobility performance is the metric this week does not touch: infrastructure failures are the one class of failure in this studio that leaves the road network entirely alone.

Into the studio

Monday uses the issued utility checkpoints alongside the unchanged Week 6 personal save. Trace the supplied capacity readings and plume evidence; do not manufacture the cascade on a student’s save or move the Week 3 upstream intake. A systemwide capacity shortfall does not establish a far-end-first outage. Cost and order both utility increments on the reverse-salient card, then upload the weekly save and evidence by 21:00. The Thursday clinic is optional follow-up. Follow the studio brief.

Assessment connection

Feeds Assessment 2 — Public Realm & Infrastructure Plan (due Week 9, 25%), principally its fiscal 30 and livability 45 criteria: the headroom decision is a fiscal argument, and the cascade is the reason it is also a livability argument. Also builds directly toward Week 10 — Resilience, which takes the same networks under hazard load, and toward the Week 12 capstone, where the corridor-scale utility argument is expected to be made once rather than per district.