Costing and energy

The price schedule every design is costed from, the rules for turning a design into a bill of materials, and exactly which loads count against the daily energy allowance.

Two hard constraints govern every design in this course: $30,000 of new spend including a required 10 % contingency, and 5 kWh a day of process energy in the peak month. Both are pass or fail, and both are checked before the marking criteria are applied.

The price schedule

$30,000 is a costing allowance, not a market quotation. Assessment uses the schedule below whatever real prices are doing, so that every design in the cohort is costed on the same basis. Lines marked indicative come from a retail listing; lines marked course assumption were set by the course.

ComponentCourse priceBasis
Polyethylene rainwater storage, supply only [S31]$130indicative
Pad, inlet/outlet plumbing, overflow, per tank$1,000course assumption
First-flush diverter and leaf screen, per downpipe$150course assumption
Pressure or transfer pump, each$700course assumption
Point-of-entry UV unit with sensor$1,200course assumption
Cartridge pre-filtration train$400course assumption
Additional roof catchment (skillion shed roof)$60course assumption
Composting toilet unit [S32]$3,500indicative
Urine diversion and storage tank$900course assumption
Greywater diversion, bathroom and laundry, installed [S33]$2,100indicative
Greywater treatment system [S33]$6,000indicative
Aquaponics: tank, 4 m2 grow bed, pump, aeration [S34]$2,500indicative
Insect rearing unit (black soldier fly or mealworm)$300course assumption
Humidified mushroom fruiting chamber$800course assumption
Hot-compost bays, set of three$500course assumption
Household anaerobic digester$1,500course assumption
Fruit or nut tree, potted, each$50course assumption
Drip irrigation, per m2 irrigated$8course assumption
Contingency10 % of subtotalcourse rule, required
indicative costThe course price schedule. Checked against fetched Australian retail listings in September 2026; see the notes below for the lines that did not hold up well.

Where the schedule is weakest

Turning a design into a bill

These rules are course assumptions, published so that two people costing the same design get the same answer.

Priced in the schedule, not drawn in the reference designs

No recipe parameter and no counted load implies these, so charging them to a threshold-setting design would inflate every threshold. You may choose them, and you pay for them from the same allowance.

Not priced by the schedule at all

Published so the allowance is not mistaken for a quotation. A real build carries these; this costing exercise does not.

What the reference designs actually cost

Until September 2026 these designs were costed from five simplified prices with no establishment, treatment, irrigation or contingency lines, which produced totals of about $3,000, $14,100 and $22,000 to $25,000. Priced against the full schedule, the excellent design came to $33,704 to $39,545 — over the allowance at every one of the five sites.

Two recipe rows changed in response and nothing else: new-storage spend fell, because the monthly tank balance saturates well below what the old recipe bought, and the excellent design's added roof catchment fell from 25 % to 5 %, because it was the most expensive water lever per point of closure. The thresholds on the method page were recomputed.

SitebaselinecompetentexcellentExcellent headroom
Canberra$11,880$23,958$27,280$2,720
Alice Springs$11,825$23,771$27,005$2,995
Brisbane$10,307$21,540$24,299$5,701
Adelaide$11,000$22,550$25,520$4,480
Darwin$12,100$24,310$27,720$2,280
indicative costReference-design totals including the required contingency, and the headroom each leaves against the allowance.

At Darwin the excellent design clears the allowance by $2,280. That is inside the noise of a screening model priced from retail listings. The published claim is that the reference designs fit the allowance as this schedule prices them, not that a real build would cost this. Treat your own design as untested if it lands within a few thousand dollars of the cap.

One bill in full

LineQuantityCost
Rainwater storage (shell)30.8 kL$4,000
Tank establishment2 tank$2,000
First-flush diverter and leaf screen4 downpipe$600
Pressure pump (domestic supply)1 ea$700
Transfer pump (garden irrigation)1 ea$700
Point-of-entry UV unit1 ea$1,200
Cartridge pre-filtration train1 ea$400
Composting toilet1 ea$3,500
Urine diversion and storage1 ea$900
Greywater diversion (installed)1 ea$2,100
Aquaponics system8 m2$4,300
Insect rearing unit1 ea$300
Hot-compost bays1 set$500
Drip irrigation450 m2$3,600
Subtotal$24,800
Contingency at 10 %$2,480
Total$27,280
indicative costBill of materials for the excellent reference design at Canberra. The baseline and competent bills are the same list with the lines their recipe parameters do not switch on removed.

Energy: what counts, and what you must declare

The allowance covers every load that runs the food, water and waste loop, reported as the peak-month average daily figure with the month named. General household appliances, the fridge, cooking, lighting, space conditioning and water heating for bathing and laundry are not counted: they belong to the proposed sequel on energy and shelter.

GroupLoadIn the model
Water movementDomestic pressure pump, garden transfer pumpmodelled
Water treatmentPoint-of-entry UV lampmodelled
Water treatmentCartridge pre-filtration (unpowered)zero by design
AquaponicsCirculation pump and aerationmodelled
Climate controlAquaculture tank heatingmodelled
SanitationComposting-toilet fanmodelled
model estimateCounted loads the screening model computes for the reference designs.

Uncertain loads are carried at their upper estimate. That rule applies to you and it applies to the reference designs, which declare 0.65 kWh/day for counted loads the screening model does not compute:

GroupLoadLowerUpper
Climate controlInsect rearing unit heating (40 W mat, winter duty)0.000.50 kWh/d
Water movementGreywater pump, if the diversion is not gravity-fed0.000.15 kWh/d
course assumptionCounted loads the model does not compute for the reference bill, carried at their upper estimate.
SitebaselinecompetentexcellentTightest headroom
Canberra2.184.013.930.99 kWh/d
Alice Springs2.253.623.551.38 kWh/d
Brisbane2.243.533.431.47 kWh/d
Adelaide2.183.483.361.52 kWh/d
Darwin2.614.013.990.99 kWh/d
model estimateDeclared peak-month load of each reference design, including the uncertain-load allowance, against the 5 kWh/day cap.

The systems the reference designs do not contain

Each of these brings its own counted loads, and the headroom above is what your additions have to fit inside. Their combined upper estimate is 1.65 kWh/day — more than Darwin has left at the competent design.

GroupLoadLowerUpper
MycologyHumidified fruiting chamber: fan and humidifier0.200.60 kWh/d
FermentationTemperature-controlled fermentation space0.050.25 kWh/d
Food preservationDehydrator for loop produce, peak-month average0.100.30 kWh/d
Waste processingDigester heating or mixing0.000.40 kWh/d
Waste processingPowered compost aeration (zero if hand-turned)0.000.10 kWh/d
course assumptionOptional systems and their counted loads. None is in the reference bill.

For scale: a four-person Australian household uses roughly 21 kWh a day of electricity in total. This allowance governs about a quarter of that, and only the quarter that runs the loop.