The assumption you didn’t notice you made#
Back of the Envelope · Week 3
£3.5 million, 1957#
The estimate for the Sydney Opera House.
Completed in 1973, at approximately A$102 million.
Do not divide one by the other#
- currency change — Australia decimalised in 1966
- sixteen years of inflation
- a client decision to expand the number of performance spaces
- Jørn Utzon’s 1966 departure and a different design for the interiors
A ratio across all of that is a precise number about nothing.
“…hadn’t been properly surveyed when competition guidelines were written.”
Bennelong Point’s geology, from the Opera House’s own published history of construction.
Ranked by likelihood#
(one way to rank these by likelihood of being wrong)
- The roof’s load can be settled once construction starts
- The design will be finalised before it matters
- The preparatory site work is already covered by the estimate
- Bennelong Point’s ground will support the design
Ranked by consequence#
(the same four assumptions, ranked by how far the answer actually moved)
- The preparatory site work is already covered by the estimate
- Bennelong Point’s ground will support the design
- The roof’s load can be settled once construction starts
- The design will be finalised before it matters
Checkable in 1957, or unresolved in 1957#
Checkable at the time — the ground: a survey could have settled it before the guidelines were even written.
Genuinely unresolved — the roof load and the final design: not withheld, not yet decided by anyone.
Your own chain’s load-bearing link#
Name the one link in your Week 2 chain you’d least like to defend.
Then ask: could you have checked it at the time — or was it genuinely still open?